Progress continues amidst challenges

Hi folks, we are continuing to make headway despite some challenges with the Chill Off test environment.  We spent the last week addressing some metering issues that cropped up and are ready to continue with the Knurr CoolTherm testing this week.  We are re-certifying the test space today to ensure all components (mechanical, electrical, compute systems, monitoring, and data reporting) are working as expected for a minimum of 6 hours (bake in period).  Provided all is working properly we will continue adjusting set points and begin gathering official test data for the CoolTherm product.  I should know more Wednesday and will update everybody with progress right here.  Stay tuned...