Third test completed!

I am very happy to announce that we successfully completed the third test in the lineup this past weekend; the Rittal LCP+ solution!  We spent the last two days quickly disconnecting the solution and moving our sensors over to the fourth solution from IBM/Vette Corp.  We had already pre-staged the Vette setup and transitioning over was fairly straightforward.  Today we are experiencing some unexpected issues with the IBM Blade Centers that were moved over and are diagnosing further.  If all goes well we expect to start official testing of this fourth solution by Friday.

 

As always, I continue to adjust the rest of the schedule accordingly and will keep each of the participants updated on their respective testing slots.  We are also working on what will be presented at the upcoming SVLG event on October 15th.  We are excited about the event and what we will have to share so expect a very interesting overview…